The comparison between Aluminum Formwork and conventional formwork is listed clearly in the below table.
| Series No. | Characteristics | Conventional Formwork | |
| 1 | Speed of construction | Four days cycle per floor | Min. Cycle time is of 1 day | 
| 2 | Quality of surface finish | Excellent. Plastering is not required | Bad. Plastering is required | 
| 3 | Pre-planning of the formwork system | Required | Not required | 
| 4 | Type of construction | Cast-in-situ Cellular construction | Simple RCC framed construction | 
| 5 | Wastage of Formwork material | Very less | In great amount | 
| 6 | Accuracy in construction | Accurate construction | Accuracy is less than Modern Systems | 
| 7 | Coordination between different agencies | Essential | Not necessarily required | 
| 8 | Resistance to earthquake | Good resistance | Less than modern systems | 
| 9 | Removing of floor slab forms without removing props 
 | Possible | Not possible | 
| 10 | Need for any timber or plywood | Not required | These are the main components | 
| 11 | Re-usage value of formwork system | 250-300 | Maximum 50 | 
| 12 | Suitability for high rise construction | The most suitable | Not suitable | 
| 13 | The initial investment in the system | High | Less | 
| 14 | Economy in Construction | Economical for mass | Economical on the small scale | 